Diamond tools are used successfully - as shown in the following two examples - in the demolition of industrial buildings as well as in the modification private homes.
Bericht in Deutsch

Chimney demolition

Klick for Video: Vorbereiten der SprengungOn 23rd February 1994 companies interested in blasting technology, council officials, many from the excited public and obviously also press and TV correspondents assembled at the BP oil refinery in the Hamburg Harbour area. At 2 p.m. it was intended to demolish a 150 metre (450 ft) high chimney built of reinforced concrete and brickwork by means of blasting technology. The blasting was also the starting signal for the complete demolition of the refinery which should be completed in 1995. Until then it was hoped to have cleared the plot of 100.000 sq. metres (25 acres) in order to build a container terminal by the Hamburger Hafen und Lagerhaus AG (Hamburg Harbour and Storage Co.). The interest in the blasting, carried out by Roller Sprengtechnik (Blasting Technology) Wuppertal was very high because the refinery was still in operation. Nearby was large storage depot and in the tubes oil and also petrol was circulating. Any mistake in the execution of the planned procedure during the blsting would have created the danger of an explosion. It was intended that the chimney falls into the southerly direction at 13.5 degrees against the north-south axis. In order that it falls into a prepared bed of earth walls, an exact preplanning was required. The necessary drilling and sawing operations in preparation of the blasting were contracted to Messrs. J. Draeger & Co. Hamburg. 

Assembly of tilting joints 


The 150 metre (450 ft) high chimney was built up to height of 135 metres (405 ft) of reinforced concrete with the Eingebaute Kippgelenkeremaining 15 metres (45 ft) of brickwork. In order to exclude an implosion of the chimney and an uncontrolled fall of the brickwork during the blasting it was intended to assemble two tilting joints. They were intended at an 170 degree angle almost opposite to each other into openings still to be provided. The o.d. of the chimney at this level was about 10 metres (33 ft). The openings had the dimensions (L x H) 2185 x 860 mm (7 x 2¾ ft). From ground level to the lower side of the opening the distance was 1140 mm (45 in) an to the upper side 2000 mm (80 in). The Schneidplanvertical cutting edges on the front side, as can be seen on the picture, were penetrating for about 400 mm (16 in) into the semicircle in the direction of the intended fall. Finally clearance cuts had to be sawn at the upper side of the opening both from inside and from outside in order to cut the chimney wall free on the opposite side to the fall direction. Prior to the commencing of the sawing and drilling operations an existing door opening was filled with concrete up to a height of 1140 mm (45 in). For the loading of the blasting material 200 holes of 40 mm Ø (1½ in) had to be drilled in the area of the tilting devices.

Perforating and sawing

It was intended that the 840 mm (33 in) long vertical cutsKlick for Video: Die Sprengung would be produced by 5 perforating holes using drills of 201 mm Ø (8 in) and that the horizontal cuts would be made by means of a wall saw. During autumn 1993 initially 4 test cores were taken from both sides of the chimney at the inner vertical lien of the intended cuts in order to calculate the basis of the static for the blasting. At a later stage the remaining 16 holes were drilled with a core drilling unit. For the sawing of the horizontal cuts a Cedima Wall Saw, Type WS-1202, was used. Especially the cutting of the lower edge of the opening an extremely accurate cutting was necessary, which had to be exactly levelled, as the tilting joints were to be mounted on this area. The swing was carried out in three stages using diamond blades of 800, 1000 and 1200 mm Ø (32, 40 and 48 in). The guide rail of 1400 mm (55 in) length was supported by two support beams which were plugged in. After reaching the length to be cut it was remounted. It followed the upper cut from the inner side from one opening to the other at a cutting depth of 120 mm (4¾ in). The reinforcement bars at the inner side of the chimney were thereby cut through. At this stage the job had to be interrupted as the autumn gales in Hamburg started. It took until February 1994 when the weather improved to such a degree that blasting could be done. On 22nd February 1994, therefore, the outer cut to a depth of 150 mm (6 in) from one opening Der ungelegte Schornsteinto the other was carried out in order to cut the outer reinforcement bars. The 200 holes of 40 mm Ø (1½ in) for the blasting holes were already drilled the previous week. The blasting was so carefully planned and perfectly executed that the chimney and the brickwork fell into the prearranged bed. During the blasting the chimney wall was destroyed to such a degree, that the broken parts could be removed without any further cutting-up operations.

Drilling and Sawing of a window opening

The owners of a detached family home felt that the lounge was too dark. In order to have a better view and improve the living quality they decided to have another window. It was planned to have a window with an upper semicircle of 1000 mm (40 in) diameter.

Bohren mit einer Bohrkrone 1000 mm
Das fertige Rundbogenfenster
The wall existed of Poroton (porous bricks) and an outer cladding of hard and glazed bricks. In order to produce the opening as quickly as possible with minimum disturbance to the environment a column drilling unit was used. This was plugged to the wall and fitted with a 1000 mm (40 in) drill bit to produce the semicircle. The straight cuts were cut manually with the K3500 ring saw. Thereby the job could be carried out according to the requirements of the proprietor with a minimum of disturbance.